|
Out-Side
Layout Construction
Back
to Layout Construction Page
As usual we learn by our
previous mistakes so 3rd time lucky I hope. I have chosen a
concrete girder method with a pile at either end to eliminate
frost heave and also if you are running long wheel based rolling
stock you need a good stable track bed. So timewill tell if this
is the correct way to go. The piles are made from 110mm/outside
diameter pipe with a single 10mm steel single rod up the
middle. The beams are made so that boxing sits on the piles and
poured in place with a 10mm bar through the centre.

Above left;
The end of the shed with the new train door fitted. It took alot
of courage & measuring before the first cut! Above middle;
First pile in place, piles were dug and poured the day before so
they are steady enough to take a beam being poured the following
day. Above right; Leveling the 2 piles before the
boxing goes on.

Above left;
Boxing on & 1st pour has been done each pour has been measured
so that it takes one barrow of concrete on the straight &
curved sections. Above middle; Everything ready for the
step & railway crossing to the shed. Above right; The
result, a centre strip of timber was added so it would take
walking traffic with out a problem.

Above left;
Now we start the grade with the top starting to desend. The 1st
curve was in place at the bottom so now we had to meet in the
middle at the same height with a constint grade!! Above middle;
4 span steel girder bridge & piers in place. Above right;
Stage one is finished with a grade of 3% to the 4 span bridge
easing to a 2% to the corner of the shed then on to level track to
& into the shed.

Above 3
Photos; These show different stages of the process, with the
curve sections & good view of the piles with the finished back
straight. The whole of ths 2nd stage has a 2% grade into the shed.
Below left ;
The last time the boxing will be used, it is in place for the
final pour. Below middle; At last! The last section has its
concrete in place & the main line is linked. Below right;
Looking at the stage 2 loop completed.

There are at
least a couple of hundred barrows of concrete in the railways
roadbed all hand mixed so I do not intend to move from our current
address in this life time!
Ballasting

One
main job on the railway was ballasting, this is not the first
time we have tried this but hopefully we will be more successful this
time. We are using a dry mixture of crusher dust, mortar, cement &
blk oxide, Above left; is the first step where a product called CE-MIX
is brushed on. This is an industrial bonding agent for giving better
adheasive strength when bonding to existing concrete. Above right; the
mixture is sprinkled on & brushed to clear flange ways, Below
left; The final step is to wet it using a garden sprayer, Below
right;

I hope this
method will give the lasting results I am looking for, I have read
alot of articles on this but with fingers crossed & a couple of
winters under our our belts, time will tell.

|